Footpath Construction Central Station

Project Summary

Our brief was to construct a footpath through Central Park Station. Whilst completing the construction of the new shared pedestrian footpath throughout the park we needed to ensure all existing parking and pedestrian facilities were free and clear with minimal disruption to commuters.

 

Project Requirements

  1. Maintain safe pedestrian access at all times.
  2. Supply and maintain traffic control and lighting
  3. Excavate, remove and reconstruct redundant footpath, including new kerbs to either side
  4. Excavate and construct raised pedestrian crossing, traffic islands, asphalt pavement and drainage grates
  5. Demolish and remove from site all spoil materials
  6. Adjust services and install signs
  7. Install new line marking

We had a 12 week window to complete the project and ran on time.